COURIER POST HIGHBROOK
Courier Post Highbrook
$17,500,000
Goodman NZ Ltd
January 2008 – January 2009
19,500m² of warehouse with single post tension (PT) slab to high flatness ratings, thought to be the largest joint-free PT slab in the world.* Two-level 2200m² office, incorporating a second storey Speedfloor suspended concrete flooring system with Eurotray and composite cladding.
With a tight 12-month timeframe, constant review of programme and methodology ensured that the warehouse and office were handed over 3 months early to allow for the installation of sorting machines.
Externally there is 10,000m² hardstand area with concrete fibre slabs, and 2200m² asphalt area for staff and customer parking.
A flagship project for Goodman, this project was also a pilot for the ESD Commercial Works Tool.